Follow the Harvard Press on FacebookFollow us on Facebook!  and TwitterFollow us on Twitter!

Wednesday, May 23, 2012  ·  Contact Us Register  ·  Subscribe/Renew  ·  Login
 
News Articles
Dredging meant to make swimming area cleaner, safer

Dredging continues at Bare Hill Pond. A loader fills a dump truck with dredged up mud. Reducing the organic matter in the pond should result in fewer weeds next summer. This view shows the town beach looking toward Blueberry Island. (Photo by Lisa Aciukewicz)
Dredging continues at Bare Hill Pond. A loader fills a dump truck with dredged up mud. Reducing the organic matter in the pond should result in fewer weeds next summer. This view shows the town beach looking toward Blueberry Island. (Photo by Lisa Aciukewicz)
A flock of gulls hop and peck their way across the mud flats, feasting on mussels. A huge yellow excavator looms over the muck like a brontosaurus looking for lunch. Clearly, some changes are under way at Bare Hill Pond.

The Bare Hill Pond Watershed Management Committee has hired CRC Company of Quincy, Mass., to dredge out silt that has accumulated in the swimming area. Dredging began the week of Dec. 12 and is expected to cvontinue for two or three weeks, according to Bill Johnson, the selectman who acts as liaison to the pond committee.

"The goal is to be done by the end of December," Johnson said.

Johnson, who is also a former member of the pond committee, said the dredging will serve three purposes. First, it will hinder weed growth by removing soil in which the weeds root, taking the bottom of the pond down to a base of glacial till.

Second, dredging will remove the benthic barrier that was installed in 1984 to suppress weeds. The barrier, now covered by silt, is no longer effective. Worse, according to Johnson, the barrier has become a hazard because its raveled edges could trap a swimmer's feet.

And third, dredging will increase the depth around the raft, where Johnson says it is now almost too shallow for diving.

Bruce Leicher, chairman of the pond committee, called the process "an example of government working well." He explained that six different permits were required for the work, but the various agencies all joined together for a single site visit in September. Among the agencies involved were the Massachusetts Department of Environmental Protection, the Army Corps of Engineers, the federal Environmental Protection Agency, and the Harvard Conservation Commission.

The permitting process usually takes six to nine months, Leicher said. But, with help from the project officer at the state DEP, permits were in place in time for the dredging to proceed this year.

Money for the project comes from a combination of state and local funds, Leicher said. A DEP grant covers 60 percent of the entire pond project, which includes other protective measures besides the dredging. The remaining 40 percent comes from local support, but not necessarily as cash. The DEP allows the pond committee to count the value of volunteer work hours toward the town's contribution, Leicher said, so the actual dollar cost to the town is quite small.

The Community Preservation Committee also provided funds for the project. A grant of $60,000 in CPC funds allowed the town to receive a $600,000 state grant.

"It's a great piece of leverage," Leicher said.

As the muck is dredged out of the pond, it is heaped in the parking area, contained by concrete barriers and heavy sheeting. Once the material has dried somewhat, Johnson says it will be trucked to the Department of Public Works site on Stow Road. The pond material will be combined with old road sand and compost to make "usable dirt," he said.

The pond committee originally intended to dredge the swimming area two years ago but was unable to do so because the six-foot drawdown in 2009 was not deep enough to expose the bottom of the bowl-shaped depression formed by previous dredging there. So the 2009 dredging operation was limited to the area around the boat ramp.

This year, the water level in the pond was drawn down seven feet, according to Leicher, six inches deeper than last year.

This year's drawdown was hindered by unusually heavy fall rains that refilled the pond even as the pump struggled to lower it. Then the power outage after the late October snow storm shut down the pump for five days, and the water level rose again. Constant backflow from the wetlands at Bowers Brook added to the problem.

The Conservation Commission has expressed concern about having the drawdown continue this late in the season. According to commission member Wendy Sisson, a late drawdown threatens turtles that live in the pond. They need to hibernate by burrowing into the mud at the bottom of the pond before a hard freeze. But if the pond's water level is constantly changing, they might be trapped out in the cold to die.

Sisson also pointed out that the prolonged pumping is expensive for the town because it uses a lot of electricity.

Conservation Commission chairman Paul Willard said the drawdown process should have a definite end date "so that everyone knows what it is and has to live with it."

Willard acknowledged that the containment area for the dredged material is working much better this year than it did in 2009.

"The water coming out of the containment area now is clean," he said, after a site visit to the pond.

Filed under: News
Comments
 
 
Post Comment
 

Name (required)

Email (required)

Website

CAPTCHA image
Enter the code shown above:


The archives below, available to logged-in paid subscribers, contain older news articles.

Numbers in parentheses indicate count of articles in the given month.

May 2012 (19)     April 2012 (24)     March 2012 (40)     February 2012 (24)     
January 2012 (22)     December 2011 (28)     November 2011 (25)     October 2011 (18)     
September 2011 (20)     August 2011 (14)     July 2011 (14)     June 2011 (25)     
May 2011 (15)     April 2011 (25)     March 2011 (22)     February 2011 (12)     
January 2011 (19)     December 2010 (17)     November 2010 (20)     October 2010 (26)     
September 2010 (18)     August 2010 (13)     July 2010 (5)     June 2010 (15)     
May 2010 (23)     April 2010 (32)     March 2010 (21)     February 2010 (16)     
January 2010 (22)     December 2009 (17)     November 2009 (22)     October 2009 (23)     
September 2009 (22)     August 2009 (13)     July 2009 (8)     June 2009 (20)     
May 2009 (47)     April 2009 (31)     March 2009 (40)     February 2009 (27)     
January 2009 (26)     December 2008 (15)     November 2008 (20)     October 2008 (25)     
September 2008 (16)     August 2008 (16)     July 2008 (5)     June 2008 (22)     
May 2008 (24)     April 2008 (23)     March 2008 (20)     February 2008 (33)     
January 2008 (19)     December 2007 (17)     November 2007 (25)     October 2007 (27)     
September 2007 (17)     August 2007 (14)     July 2007 (5)     June 2007 (25)     
May 2007 (29)     April 2007 (23)     March 2007 (23)     February 2007 (22)     
January 2007 (20)     December 2006 (18)     November 2006 (6)     

CLICK AN AD!
Dinner at Deadline
Bull Run Restaurant
Harvard Custom Woodworking
Turbo Lube
Whole Earth
Inspired Design
Harrod, Warren
Pinards
Global Fitness
Merrill Excavating
Copyright 2006–2012 by The Harvard Press LLC  ·  PO Box 284  ·  Harvard, Massachusetts 01451  ·  Phone 978.456.3700  ·  Fax 978.274.5605  ·  Terms Of Use  ·  Privacy Statement  ·  Site Credit